Essential improvements completed at A27 Langstone Interchange
VolkerLaser was appointed by National Highways as principal contractor to deliver essential refurbishment at the A27 Langstone Interchange near Portsmouth.
The full scope of works included concrete removal and reinstatement, waterproofing, resurfacing, replacement of the Vehicle Restraint System (VRS), parapet replacement and expansion joint replacement.
Works commenced in June 2026, beginning with the removal of the verges and concrete barriers. These areas were stripped back to deck level, waterproofed, and reinstated, including new kerb lines, concrete barriers and slabs, and surrounding surfacing. This phase was successfully completed on both the eastbound and westbound carriageways.
Following completion of the verge and central reservation works, the narrow lane restrictions were removed, and the project then progressed to the bridge deck refurbishment phase, which included refurbishment of both the eastbound and westbound carriageways. The existing surfacing was removed down to deck level before waterproofing and reinstatement works were completed, followed by resurfacing and white line application. In addition, a total of eight new expansion joints were successfully replaced.
All works were delivered under carefully planned traffic management arrangements. Narrow lane restrictions were utilised throughout the central reservation and verge phases, allowing the dual carriageway to remain open to the public during daytime hours. Construction activities were primarily undertaken during overnight full closures, with full weekend closures implemented to facilitate the bridge deck refurbishment works.
At VolkerLaser, we are committed to the responsible and professional management of the environment throughout our construction activities. During two of the full weekend closures, the project team took the opportunity to undertake a litter-picking initiative along the 500-metre stretch of carriageway, removing accumulated debris and helping to improve the local environment.
Throughout the scheme, the team successfully overcame several challenges. The presence of a subway beneath the bridge created level differences between the subway roof and the bridge deck, requiring the waterproofing and surfacing works to be completed in stages. As a result, four weekend closures were required to complete all the works. Despite these challenges, the team maintained excellent coordination between multiple contractors and stakeholders, ensuring that the project was delivered safely, efficiently and to a high standard. The project was successfully completed in mid-October 2026.